 |
 |
 |
ESWP:
International Bridge Conference®: ABC Construction
ABC Construction
Tuesday, June 3, 2008
8:30AM to 12:00PM
Chair: Mary Lou Ralls, PE, Ralls Newman, LLC, Austin,
TX
IBC 08-23 - An Owner's Perspective on Implementing an Accelerated
Bridge Construction Program
James C. McMinimee, PE, Utah Department of Transportation, Salt Lake
City, UT; Carmen E. L. Swanwick, HDR Engineering, Inc., Salt
Lake City, UT
The Utah Department of Transportation has successfully implemented
prefabricated bridge systems and accelerated bridge construction on
ten projects utilizing different elements and technologies from full-depth
prefabricated precast concrete deck panels, prefabricated precast concrete
bent caps, total superstructure systems, self propelled modular transport
practice, to temporary bridge use. This article discusses the organizational
lessons learned from implementing Accelerated Bridge Construction.
IBC 08-24 - Accelerated Replacement of the 4500 South Bridge
over I-215 in Salt Lake City, UT using SPMT's
Michael Arens, Michael Baker Jr., Inc., Salt Lake City, UT; Boyd
Wheeler, Utah Department of Transportation, Salt Lake City, UT
The 4500 South Bridge over I-215 in Salt Lake City, UT required replacement
due to structural deficiencies. The Utah Department of Transportation
(UDOT) required Accelerated Bridge Construction (ABC) techniques to
minimize traffic impacts, improve work zone safety, and move forward
the use of ABC for future projects. UDOT , Michael Baker Jr., Inc, and
the Contractor evaluated several bridge types and ABC options, and decided
on the use of Self Propelled Modular Transporters (SPMT's) to move the
bridge superstructure into place.
IBC 08-25 - Accelerated Bridge Construction Using Precast Piers
Eric Yermack, Arora and Associates, P.C., Lawrenceville, NJ
The Route 70 over Manasquan River project utilized a unique precast
pier solution to construct a replacement bridge. The precast system
consisted of architectural, HPC pier columns, caps and cofferdams with
post-tensioning. The method of construction satisfied environmental
requirements and produced a signature bridge over 700 days ahead of
schedule.
IBC 08-26 - Accelerated Bridge Re-decking of Bridges on the George
Washington Memorial Parkway
Donald Miller, PE, Eastern Federal Lands Highway Division, Sterling,
VA; W. Jay Rohleder, Jr., PE, SE, FIGG, Exton, PA
Successful use of prefabricated panels achieved accelerated bridge
re-decking on the heavily traveled (40,000 ADT) George Washington Memorial
Parkway. This innovative application of segmental bridge consruction
methids was implemented on three bridges and developed to keep traffic
moving while installing high-strength low maintenance new bridge decks.
IBC 08-27 - Rapid Replacement of the Hood Canal Bridge Approach
Spans
Joseph Merth, PE, Washington State Department of Transportation, Olympia,
WA
To minimize traffic impacts the Washington State Department of Transportation
developed an innovative method to replace the Hood Canal Floating Bridge
Approaches in two weekend closures. The single-span 154' west approach
was replaced in 51 hours, and the five - span 605' east approach was
replaced in 49 hours.
IBC 08-28 - Rapid Replacement of the Island Park Drive Overpass
Michel Vachon, McCormick Rankin Corporation, Ottawa, ON, Canada;
Quazi Islam, Ministry of Transportation Ontario, Kingston, ON, Canada
The Island Park Drive Overpass carrying over 150,000 vehicles / day
on Highway 417 in Ottawa, Ontario, Canada is at the end of its lifespan.
It was decided to replace it using rapid replacement techniques with
an overnight highway closure. The replacement was successfully completed
in August 2007 in 17 hours.
IBC 08-29 - Hyper Design /Hyper Build ~ It Can Work
Thomas Anella, PE, Rama Krishnagiri, PE, PB, Princeton, NJ; Manu
Patel, PE, New Jersey Department of Transportation, Trenton, NJ
NJDOT's I-280 Stickel Bridge Rehabilitation is a Hyper-Design/Hyper
Build Project. The 32-month original design schedule was reduced to
15 months and the 3-year staged construction cut to 21 months. The project
is a success as the aggressive schedule is being met, due to all parties
working together in perfect harmony to reopen all lanes with minimal
disruption.
This page was last modified:
|
 |